Transformer to Edison NJ

About This Project

Client came to SPL needing heavy haul transport to New Jersey area before end of the year.  

CommodityTransformer
Date2019
ScopeTransportation, Heavy Haul, Offloading

Result Driven

Route survey was done within 4 days and permits were worked on immediately after survey was complete.

SPL and their heavy hauler wa able to find a suitable route to get permit approval.  The transformer was delivered successfully within time frame for customer. 

Solution

SPL Delivered:

  • Permits
  • Unit Loaded and stored onsite until customer released.
  • Route survey
  • Transload to smaller SPMT configuration and delivery inside sub, crane offload to pad.